One formula for dosage per metre, a table for common joint sizes, and the three time points (skin, full cure, watertight) that decide whether a joint has to be cut out and redone.

Under-ordering stops the site; over-ordering leaves drums that expire. Judging the cure time too early means the bead is flooded before it cures and the whole joint has to be cut out. Both problems are common on site and both are solved by one formula and three time points.

The dosage formula

Sealant consumption depends on three things only: joint width, joint depth and compound density.

kg per metre = width (mm) × depth (mm) × density (g/cm³) ÷ 1000

Measured density is 1.6 g/cm³ for polysulfide and 1.52 g/cm³ for two-component polyurethane. Use 1.5–1.6 for estimating.

Worked example: a 20 × 20 mm joint

20 × 20 × 1.6 ÷ 1000 = 0.64 kg/m

Add 5–10% for application loss: order about 0.67–0.70 kg/m.

Common joint sizes

Width × depthkg/m at 1.6 g/cm³Order with 8% loss
10 × 10 mm0.160.17
15 × 15 mm0.360.39
20 × 20 mm0.640.69
25 × 25 mm1.001.08
30 × 30 mm1.441.56
20 × 30 mm0.961.04

Two-component products ship as separate A and B components. Calculate on the combined mixed weight, not on the A component alone — this is the most frequent cause of mis-ordered quantities.

Deeper is not stronger

A thicker bead feels safer but behaves worse. The sealant only works if it can stretch when the joint opens. Excessive depth concentrates stress at the bond line and promotes debonding.

Normal practice: depth = 0.5–1.0 × width, and not more than 20 mm. Where the design calls for more, place closed-cell PE foam board as a backer to bring the actual bead depth to the design value and to prevent three-sided adhesion.

The backer must be closed-cell. Open-cell foam absorbs water and wicks it to the bottom of the joint.

Three time points, not one

Skin formation. Surface films over and stops being tacky. Measured 10 h for polysulfide and 5 h for two-component polyurethane (both required ≤24 h). A skinned surface says nothing about the interior.

Full cure. At 25 °C, polysulfide needs 3–7 days and two-component polyurethane about 7 days to reach tensile strength and waterproofing performance. Lower temperature and higher humidity both slow it down. At around 5 °C in winter, polyurethane can take 10–14 days.

Watertight, backfillable, trafficable. Only after full cure.

StagePolysulfide at 25 °C2K polyurethane at 25 °C
Skin formationabout 10 habout 5 h
Handling strength24 h24 h
Full cure3–7 days7 days
Fill / trafficafter full cureafter full cure

Basins and canals must not be filled until the sealant is fully cured. Water on an uncured bead seals the surface and the interior never reaches design strength — effectively an untreated joint.

Mixing is not negotiable

Two-component products are normally mixed A:B = 10:1 by weight, with some batches between 100:8 and 100:12. Follow the product datasheet.

  1. Weigh on a scale. No volume ratios, no eyeballing. Keep error within ±1–5%.
  2. Mix with a power stirrer for 3–5 minutes until the colour is uniform with no pale streaks.
  3. Mix only what can be placed within the tooling life. 8.5 h for polysulfide, 3 h for two-component polyurethane.

The consequences of a bad ratio are predictable: too little B and the bead stays soft and never cures; too much B and it cures brittle, loses elasticity, and polysulfide may suffer reverse vulcanisation with no remedy.

Two things sites overlook

The substrate must be dry and free of laitance. Laitance has almost no strength, so sealant bonded to it is bonded to dust. Grind back with a wire brush or angle grinder and blow out the dust. Damp substrates need mechanical drying, not a rush to beat the programme.

The joint must be free of oil and grease. Oil destroys the bond interface, and the metres that debond are usually the ones that were contaminated.

Get dosage, ratio and curing right and the leak rate drops by an order of magnitude. The remaining variable is grade selection: see polysulfide versus polyurethane.

Author: Technical Department, Hebei Hualing Rubber Co., Ltd.. Reviewed against third-party test reports and the standards cited above.

Related products

References

  1. JC/T 483-2022《聚硫建筑密封胶》

Contact

Company
Hebei Hualing Rubber Co., Ltd.
Address
No.97, Xifantun Village, Wuqiang Town, Wuqiang County, Hengshui City, Hebei Province, China
Contact
Mr. Hou (Sales Manager)
Tel
+86 13081809758
Email
mifengjiaochang@163.com
Need a recommendation or a quote?

Tell us the joint width, movement, medium and temperature — we will match the right product and quote ex-works.